Chemical Distribution Facility in Central Scotland, Southern England, and South Wales
« All Projects

Geosyntec Consultants (Geosyntec) U.K. office (formerly Ford Consulting Group) has been retained to assist a multinational chemical distribution business in understanding and addressing contaminated land liabilities at their three of their main UK facilities, located in Central Scotland, Southern England and South Wales. The sites are active and the remedial solutions were designed to minimize any disruption to their on-going operations.

Geosyntec’s Scope of Services

Geosyntec’s work program has included detailed ground contamination source audits coupled with intrusive site investigations and monitoring to understand residual soil and groundwater contamination. The main contaminants of concern were the chlorinated solvents TCE/PCE and their breakdown products. Where risk assessment has indicated issues of potential concern, further intrusive investigations, remedial feasibility and design studies have been undertaken. This has taken place at all three sites in the past 1-3 years. Remedial solutions implemented or on-going include soil vapor extraction, groundwater treatment and in-situ bioremediation of chlorinated solvents in both soil and groundwater.

Notable Accomplishments

At the priority site a remedial scheme involving soil vapor extraction and shallow groundwater collection and treatment was successfully completed after two years with the recovery of around 1.8 tons of chlorinated solvents from a dual porosity bedrock aquifer and the overlying soils. Post remediation validation works included soils analysis and a vapor intrusion assessment coupled with a one-year groundwater monitoring exercise. The rebound concentrations of solvents in groundwater through back diffusion from the bedrock matrix were below the agreed risk based remedial targets defined for the project. The validation works were undertaken to satisfy the Environmental Agency, Local Authority and landlord. They were completed in early 2012 and written confirmation from the stakeholders of their satisfaction that the remedial objectives have been met has been received.

Remedial works at the second and third sites have recently commenced and are scheduled to continue until the end of 2013. One site is utilizing a soil vapor extraction coupled with shallow groundwater collection and treatment approach. Current monitoring data indicate that this system will achieve the remedial targets within a 9 month operation period and a 12 month post remediation monitoring program is planned.

The remedial approach for the third facility involves in-situ enhanced reductive dechlorination of the residual solvent contamination in four hotspot areas sourcing on-going impacts to groundwater quality. Following detailed natural attenuation studies it was concluded that groundwater plumes from two areas of residual contamination were being fully degraded within the site boundary but that reductive dechlorination was stalled in the four remaining areas. The injection of an organic substrate to enhance the reductive dechlorination process has been undertaken and initial monitoring data indicate a strong response in the rates of solvent degradation.

Quick Qual

No pages found in your document. What is a Quick Qual?

Project Summary

  • Location: Central Scotland, Southern England and South Wales
  • Client: Confidential
  • Project Practice Areas: Contaminated Sites
  • Type of Facility: Chemical Distribution Facilities
  • Services Provided: Ground contamination source audits, Site investigations and monitoring, Quantitative Risk Assessment, Bioassay and remedial pilot trials, Soil and groundwater remediation, Regulatory liaison and licensing
  • Type of Work: Site Remediation
  • Governing Regulation: Federal and Local